Report Summary
This is the Approved Minute documented for the Forensic Services Committee held on 4 May 2023. The Minute was approved at the meeting on 10 August 2023.
Meeting
The publication discussed was referenced in the meeting below
Forensics Services Committee - 10 August 2023
Date : 10 August 2023
Location : online
Project Weaver – Outcome Report
Members were provided with a closure report presented by AConnell. During discussions the following matters were raised;
The Chair sought assurance that equipment is now being used and fully functional following previous delays. AConnell advised about 90% of instrumentation is currently live as some items of kit required snagging work to be done. Delays in getting some instruments installed was due to the economy and supply chain at that time, with a lot of the kit coming from overseas. The Chair sought clarity over networking issues mentioned in the report and asks what risks were associated and mitigations in place. AConnell explained the rationale around the networking issues with BT and Police Scotland however assured members that they were granular issues being dealt with on the ground.
The Chair noted the complexity of the project and congratulated all those involved.
Members NOTED the report